Residents Come Out In Droves To Speak Against Elcon; Township To Hold Special Meeting


Credit: Elcon

Falls Township Board of Supervisors Chair Bob Harvie made a clarification ahead of public comment this week regarding the controversial Elcon hazardous waste treatment facility plan.

Harvie’s clarification was made to address what the elected official called an incorrect statement made by Pennsylvania Department of Environmental Protection (DEP) officials at the recent Elcon meeting at the Sheraton.

Advertisements


According to Harvie, a statement by the DEP said Falls Township officials have the ability to change the zoning on a property – which could, in theory, forbid Elcon from building at the Keystone Industrial Port Complex U.S. Steel site. Harvie noted the township does not have the authority to “randomly change the zoning on a private piece of property.”

Property owners, of course, do have the ability to ask that their zoning is changed, and it would be the township’s authority to admit that change or not but such a change cannot be done without the property owner’s approval and input.

Numerous residents gathered after Harvie’s statement to once again pledge theirย disapproval for the hazardous waste recycling facility. Most of which called the companies use of the term recycling is nothing but a ploy to hide their polluting system.

Advertisements


Other residents spoke of the financial ruin that could come back on the township if Elcon were to have a spill. They raised concern that area businesses would be forced to close for several days due to lack of water, and those affected could potentially sue the township for the hardship. A resident even cited that Elcon wouldn’t be responsible if a spill occurred off property, leading to potential catastrophic issues for the Philadelphia area.

DEP officials are continuing to reviewย Elconโ€™s lengthy application for construction of aย facility on a 22-acre portion of a 33-acre property in theย Keystone Industrial Port Complex, which is made up of U.S. Steelโ€™s massive Fairless Works site. The Israel-based company has applied for aย Solid Waste Management Permit for a Commercial Hazardous Waste Treatment and Storage Facility, an Air Quality Plan Approval, and a General Stormwater Discharge permit.

Advertisements


According to officials, the facility will only accept liquid waste via truck fromย pharmaceutical manufacturing,ย petroleum refineries, chemical facilities, and semiconductor manufacturing. It will process between 150,000 to 210,000 tons a year of wastewater using chemicals,ย sludge filtration, thermal treatment, steam stripping, distillation, salt concentration, salt crystallization, and salt drying processes. The leftover solid waste will be transported by truck to an off-site permitted hazardous waste landfill.

Waste Management landfills in Falls Township are not permitted to accept waste from Elcon and can only take what is termed municipal refuse.

Elcon officials have previously said the water processed at their proposed facility will be clean, but it will not be released into area waterways or water systems. Instead, the treated water will be used to cool the facilityโ€™s equipmentย or evaporated through aย closed-loop system.

Advertisements


The Planning Commission will hear a proposal by Elcon next week. The planning commission, unlike the Zoning Hearing Board, does not have legal stance over issues and only acts as an advisory board to make recommendations. The Elcon matter is the only item on the commission’s agenda.

Falls Township will hold a special meeting on April 30 for the public to provide comment on the issue. A location for that meeting has not yet been determined but it will likely be held at a school within the Pennsbury School District.

Advertisements



Related:



Report a correction via emailย |ย Editorial standards and policies