The northbound Maple Avenue (Route 213) ramp onto Route 1 will be closed starting Friday.

Credit: Tom Sofield/LevittownNow.com
The closure and detour will begin Friday at 9 p.m. and end Monday at 5 p.m.
Advertisements
“During construction, Route 213 motorists wanting to access northbound Route 1 take Route 1 South, South Bellevue Avenue, Gillam Avenue, Route 413, South Bellevue Avenue and follow to the ramp for northbound Route 1. Motorists are advised to allow extra time when traveling through the area,” PennDOT said in a press release.
The work is part of a project to replace the three-span, pre-stressed box beam bridge over Maple Avenue. The reconstruction project will realign the Route 1 ramps to Maple Avenue, resurface the roadway approaches and ramps, install glare screens on the median barrier and upgrade drainage systems.
During the project, the speed limit along the highway was been reduced in the work zone.
Advertisements
The work on the project should be done by October 2014.