Neshaminy Says Bids For New School Came In Lower Than Expected


The current Tawanka School. Credit: Tom Sofield/LevittownNow.com
The current Tawanka School.
Credit: Tom Sofield/LevittownNow.com

The Neshaminy School Board voted to approve bids for nine contract packages for construction of the new 900-student building at the site of the Tawanka School on Brownsville Road in Lower Southampton.

District officials said the bids came in 10.4 percent under expectations. The bids, barring no overages during construction, put the total anticipated cost at $26 million.

Advertisements


The board voted 7-2 to approve the bid packages to the lowest and most responsible bidders. Members Ron Rudy and Mike Morris voting against the bids.

The low bids for the project, which was anticipated to cost between $30 million to $34 million, will allow Neshaminy to include alternate project additions. The additions to the project include extra storage cabinets in all classrooms, three bus canopies outside the school, and automated lighting controls to enhance energy savings during daylight hours, according to a statement.

“Project bid costs were driven down by diligent value engineering and scope selection, as well as competition generated from a significant bid solicitation effort,” the statement read.

Advertisements


In March, the Lower Southampton Board of Supervisors unanimously approved preliminary and final land development for the new school, which will house 40 classrooms inside a two-story structure. Officials have said the school will be able to hold approximately 900 students.

District officials have said they are aiming to open the new school in time for the 2016-2017 school year.

The current school at the Tawanka site is expected to be torn down before construction on the new building will begin. The Bucks County Intermediate Unit has leased that building but will move to the soon-to-be-closed Samuel Everitt Elementary School in Levittown.

Advertisements


The district believes the consolidation plan that will construct a new school, upgrade several and close up to three will save Neshaminy millions money over time.

Morris tried to pass a motion that would delay voting on the bids until after the primary election. Rudy cast the lone vote in support.

Morris inquired to solicitor Tom Profy III whether the district would face financial consequences if the project was stopped or amended if a new board was elected. He answered that the district could back out of the contracts, but it had to be for a just reason and there would be financial penalties.

Advertisements


Spiezle Architectural Group is designing the school and Reynolds Construction has been appointed the site manager.

Report a correction via email | Editorial standards and policies