The plan for three new regional elementary schools in Bristol Township will come before the township’s Zoning Board Monday night.
At the 7 p.m. meeting, which is going to held at the township building on Bath Road, the district will ask for several variances for the project that will require the demolition of the current nine schools and construction of three new buildings, officials said.
Advertisements
The new schools would be built at the current sites of James Buchanan, Ralph Waldo Emerson Mary Devine elementary Schools.
The three new schools are each designed to house 1,300 students and would be divided into two sections. Kindergarten through second grade in part of the building and third through fifth grade in the other section of the facility. District officials said previously that the parking and student pick-up situation that plagues many schools is expected to improve with the new schools.
Click here to see renderings of what the new schools would look like
Advertisements
The estimated $152.6 million facilities overhaul would close Franklin D. Roosevelt Middle School; Neil A. Armstrong Middle School and the former Benjamin Franklin School, currently home to the district administrative staff, would be renovated for students. Harry S. Truman High School would not see any major work done. Clara Barton Elementary School would be re-purposed into the administration and maintenance building.
The new schools would be constructed on the land next to the standing schools and students would not be displaced, construction manager Bill Reynolds said. District officials said recently that the Devine site in Croydon is running into some issues and students might be displaced to other buildings during construction.
A resident at Buchanan called for the district to put the building vote up for referendum. Lee reiterated that the district has no plan to put the project on the ballot.
Advertisements
“Time is of the essence,” Superintendent Dr. Samuel Lee told residents at a community meeting last month. “Not building these schools will be more costly to the community and school district.”
The plan still needs to go before other township and county boards.
The district recently released a project timeline for the project:
- September 2013: The district will hold required closing and construction hearings
- December 2013: The bid process for the project will begin
- Early 2014: Construction to begin
- September 2015: The new schools will open for students