Lane Shift Happening As Part of Route 13 Project


route 13 graphic

Provided by Safer13.com:

Credit: Tom Sofield/LevittownNow.com
Advertisements


A traffic pattern switch is scheduled to occur Monday, July 8, on U.S. Route 13 (Bristol Pike) in Bucks County, for PennDOT’s $36.5 million project to rebuild and improve four miles of the highway.

Beginning Monday, July 8, southbound Route 13 (Bristol Pike) traffic will be shifted over to the southbound side of the highway at Beaver Dam Road through September to allow the contractor to rebuild the center section of the highway.

Beaver Dam Road is expected to reopen on July 8 just north of Route 13 (Bristol Pike) in Bristol Borough and Bristol Township following after the rehabilitation of the bridge over Adams Hollow Creek. Upon reopening Beaver Dam Road motorists will only be able to turn right to continue south on Route 13. Motorists wanting to access northbound Route 13 from Beaver Dam Road will take Route 13 South and follow it to the Bath Road jug handle and turn left onto Route 13 North.

Advertisements


PennDOT is enhancing travel and safety along a 4.3-mile stretch of Route 13 (Bristol Pike) by rehabilitating the deteriorated pavement; rebuilding  bridges;  replacing drainage facilities that date back to the 1940s; building sidewalks for pedestrians; installing medians; removing jug handles; reducing travel speeds; and implementing traffic calming measures.

James D. Morrissey, Inc. of Philadelphia is the general contractor on the $36,527,577 project that is financed with 100 percent federal funds. The entire project is expected to finish in October 2015.

For updated Route 13 Improvement Project information motorists can log on to www.safer13.com.

Advertisements


More Route 13 News:

Report a correction via email | Editorial standards and policies